When must the Corrective Action Plan be approved by the governing body?

Get more with Examzify Plus

Remove ads, unlock favorites, save progress, and access premium tools across devices.

FavoritesSave progressAd-free
From $9.99Learn more

Improve your knowledge of the Municipal Budget Process. Familiarize yourself with key concepts and terminology through multiple choice questions and detailed explanations. Prepare effectively for your exam!

The approval of the Corrective Action Plan must occur within six months of the budget year close because this timeframe allows for an adequate assessment of the audit findings and the necessary adjustments to be made. By ensuring that the plan is approved within this period, the governing body can address any deficiencies and implement corrective measures that will improve operations and compliance going forward. This timeline is integral for maintaining accountability and ensuring that any identified issues are resolved promptly, which contributes to the overall financial health and transparency of the municipality. This process aligns with best practices in budget management and ensures that lessons learned from the previous budget year are incorporated into future planning and operations.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy